MIT Services Status

Building-24: Power Shutdown
Scheduled Maintenance Report for MIT
Completed
The scheduled maintenance has been completed.
Posted 10 days ago. Jun 16, 2017 - 07:00 EDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted 11 days ago. Jun 15, 2017 - 22:00 EDT
Scheduled
All normal power in the building including but not limited to all HVAC equipment, LNS server rooms, 5th floor server room, IS&T room 114T, all office receptacles and lighting, and the elevator will be affected. Both wired and wireless networking will be unavailable.

Any questions please contact Mike DeRoche @ 617-866-0290.
Posted 11 days ago. Jun 15, 2017 - 13:23 EDT